Cost Management & Earned Value

๐Ÿ’ฐ Cost Management & Earned Value

Study Notes โ€” Page 4  |  ClearPMPExam.com

4-Step Process Reserves EVM Basics All 8 Formulas CPI & SPI Worked Example

1. What is Cost Management?

Definition

Cost Management involves planning, estimating, budgeting, and controlling project costs so that the project is completed within the approved budget.

Simply put โ€” it is the process of making sure you don’t run out of money before the project is done, and that every rupee spent is delivering value. Cost Management is where the famous Earned Value Management (EVM) formulas live โ€” and EVM is the single most tested topic in the entire PMP exam.

๐Ÿฅ Real Example โ€” Pharma Campaign

A pharma company approves โ‚น20 lakh for a digital campaign. Cost Management means: estimating how much each activity costs (videos, ads, web), adding reserves for risks, getting approval for the final budget, then tracking every week whether you’re spending in line with the work being done โ€” not just whether money is left.

๐Ÿ‘‰ A project can be “under budget” in terms of cash spent but still be in trouble if the work isn’t keeping pace. EVM tells you the real picture.


2. The 4-Step Cost Management Process โ€” In Order

1

Plan Cost Management

Decide how costs will be estimated, structured, monitored, and controlled throughout the project. Sets the rules for everything that follows.

Output โ†’ Cost Management Plan
โ†“
2

Estimate Costs

Calculate the cost of each activity and resource. Uses Analogous, Parametric, Bottom-Up, or Three-Point estimation. Also estimates contingency reserves for identified risks.

Output โ†’ Cost Estimates, Basis of Estimates
โ†“
3

Determine Budget

Aggregate all estimated costs to establish the Cost Baseline โ€” the approved time-phased budget used for performance measurement. Management Reserve is added on top to get Total Project Funding.

Output โ†’ Cost Baseline, Project Funding Requirements
โ†“
4

Control Costs

Monitor actual spending against the baseline. Use Earned Value Management (EVM) to measure true project performance. Identify variances, forecast final cost, and manage changes.

Output โ†’ Work Performance Information, Cost Forecasts, Change Requests

3. Reserves โ€” Contingency vs Management

Before the budget is finalised, two types of extra money are set aside for risk. The exam consistently tests which reserve is for what, and who controls each one.

๐Ÿ”ต Contingency Reserve

For known risks โ€” risks that have been identified and planned for in the Risk Register.

Example: You know there may be vendor delays. You add โ‚น1 lakh buffer for this known risk.

This reserve is inside the Cost Baseline.

Controlled by: Project Manager

๐Ÿ”ด Management Reserve

For unknown risks โ€” surprises that were not anticipated during planning.

Example: A sudden regulatory change requires unplanned rework. Management Reserve covers this.

This reserve is outside the Cost Baseline.

Controlled by: Senior Management

How the Budget Stacks Up

Work Package Costs
โ†’ All activity costs added up
Work Package Costs
+ Contingency
= Cost Baseline (PM controls)
Work Package Costs
+ Contingency
+ Mgmt Reserve
= Total Project Funding

๐Ÿ“Œ Cost Baseline = All activity costs + Contingency Reserve (excludes Management Reserve)

๐Ÿ“Œ Total Project Funding = Cost Baseline + Management Reserve

๐Ÿ“Œ EXAM TIP โ€” Most Tested Distinction

Cost Baseline does NOT include Management Reserve. EVM performance (PV, EV, AC) is always measured against the Cost Baseline, not Total Project Funding.

๐Ÿง  Memory Trick

Contingency = PM’s safety net (known risks). Management Reserve = Management’s emergency fund (unknown shocks). PM can dip into Contingency. Only management unlocks the Management Reserve.


4. Earned Value Management โ€” The 4 Core Terms

What is EVM?

Earned Value Management is a method for measuring true project performance by comparing the value of work planned vs work completed vs money actually spent โ€” all at the same point in time.

The genius of EVM is that it answers a question that a simple budget report cannot: “Yes, we’ve spent โ‚น30,000 โ€” but are we getting โ‚น30,000 worth of work done?” EVM tells you whether you are ahead, behind, over budget, or under budget โ€” all in one set of numbers.

PV
Planned Value

The budgeted value of work you planned to complete by this point in time.

PV = % planned work ร— BAC

EV
Earned Value

The budgeted value of work you actually completed โ€” regardless of what it cost.

EV = % work done ร— BAC

AC
Actual Cost

The actual money spent so far to complete the work done.

Always given in the question

BAC
Budget at Completion

The total approved budget for the entire project โ€” the original plan.

Always given in the question

๐Ÿ“Œ EXAM TIP โ€” Always Calculate EV First

In every EVM question, calculate EV first. EV sits in the middle โ€” it’s used in both CPI (EV รท AC) and SPI (EV รท PV). If you get EV wrong, every other number is wrong. EV = % work done ร— BAC.


5. All 8 EVM Formulas โ€” The Complete Set

These 8 formulas cover every EVM question in the exam. Learn the formula, the interpretation, and the trigger word for each one.

Formula Calculation What it tells you Key rule
CV โ€” Cost Variance EV โˆ’ AC Positive = under budget โœ…
Negative = over budget โŒ
Negative CV = spending more than work delivered
SV โ€” Schedule Variance EV โˆ’ PV Positive = ahead of schedule โœ…
Negative = behind schedule โŒ
Negative SV = less work done than planned
CPI โ€” Cost Performance Index EV รท AC >1 = under budget (efficient) โœ…
= 1 = on budget
<1 = over budget โŒ
CPI 0.85 = for every โ‚น1 spent, only โ‚น0.85 value delivered
SPI โ€” Schedule Performance Index EV รท PV >1 = ahead of schedule โœ…
= 1 = on schedule
<1 = behind schedule โŒ
SPI 0.8 = only 80% of planned work is done
EAC โ€” Estimate at Completion BAC รท CPI Expected FINAL cost of the project if current efficiency continues Most common EAC formula in exam
ETC โ€” Estimate to Complete EAC โˆ’ AC How much money is still needed to finish the project Remaining cost from today to completion
VAC โ€” Variance at Completion BAC โˆ’ EAC Positive = will finish under budget โœ…
Negative = will finish over budget โŒ
Positive VAC = profit. Negative VAC = loss.
TCPI โ€” To Complete Performance Index (BAC โˆ’ EV) รท (BAC โˆ’ AC) Efficiency needed in remaining work to finish within original budget TCPI > 1 = must work more efficiently than before

6. How to Read CPI and SPI โ€” Traffic Light Guide

When the exam gives you a CPI or SPI number, you need to instantly know what it means. Use this traffic light interpretation.

CPI โ€” Cost Performance Index (EV รท AC)

CPI > 1 โ€” Under budget. Getting more value than money spent. โœ…
CPI = 1 โ€” Exactly on budget. Every rupee delivering exactly โ‚น1 of value.
CPI < 1 โ€” Over budget. Getting less value than money spent. โŒ

SPI โ€” Schedule Performance Index (EV รท PV)

SPI > 1 โ€” Ahead of schedule. More work done than planned. โœ…
SPI = 1 โ€” Exactly on schedule. Work done matches plan perfectly.
SPI < 1 โ€” Behind schedule. Less work done than planned. โŒ
๐Ÿง  Memory Trick โ€” Greater Than 1 is Always Good

For both CPI and SPI: >1 = good news. <1 = bad news. = 1 = perfect. Simple as that. The same rule works for both indices.


7. Full Worked Example โ€” Step by Step

The exam always gives you a scenario with numbers. Here is how to solve any EVM question, using the exact method from your notes.

๐Ÿงฎ Example โ€” Pharma App Project

Given: BAC = โ‚น80,000  |  Total Duration = 8 months  |  Time Elapsed = 4 months

Given: Work Completed = 40%  |  Actual Cost (AC) = โ‚น30,000

1
Calculate EV first: EV = % work done ร— BAC = 40% ร— โ‚น80,000 = โ‚น32,000
2
Calculate PV: % planned = time elapsed รท total = 4 รท 8 = 50%. PV = 50% ร— โ‚น80,000 = โ‚น40,000
3
Calculate CPI: CPI = EV รท AC = โ‚น32,000 รท โ‚น30,000 = 1.07 โ†’ Under budget โœ…
4
Calculate SPI: SPI = EV รท PV = โ‚น32,000 รท โ‚น40,000 = 0.80 โ†’ Behind schedule โŒ
5
Calculate EAC: EAC = BAC รท CPI = โ‚น80,000 รท 1.07 = โ‰ˆ โ‚น74,766 โ†’ Will finish under original budget โœ…
6
Calculate ETC: ETC = EAC โˆ’ AC = โ‚น74,766 โˆ’ โ‚น30,000 = โ‚น44,766 โ†’ Remaining cost needed to finish
7
Calculate VAC: VAC = BAC โˆ’ EAC = โ‚น80,000 โˆ’ โ‚น74,766 = โ‚น5,234 โ†’ Positive = will come in under budget โœ…
โœ… Cost: Under budget (CPI 1.07)
โŒ Schedule: Behind schedule (SPI 0.80)

Key insight from this example: The project is spending money efficiently (good CPI) but the team is completing less work than planned (bad SPI). This means they are working slowly but not wastefully. The PM needs to accelerate pace โ€” not cut costs.


8. How to Calculate EV and PV When Not Directly Given

Sometimes the exam doesn’t give you EV or PV directly. You have to calculate them from the information provided. There are two common scenarios.

ScenarioWhat’s givenFormula to useExample
% work completed is given BAC + % complete EV = % complete ร— BAC 40% done, BAC โ‚น80,000 โ†’ EV = โ‚น32,000
% planned not given, but time is given BAC + time elapsed + total duration % planned = time elapsed รท total duration
PV = % planned ร— BAC
4 months of 8 done โ†’ 50% planned โ†’ PV = โ‚น40,000
AC is always just given AC stated directly No calculation needed AC = โ‚น30,000 (just use it)
BAC is always just given BAC stated directly No calculation needed BAC = โ‚น80,000 (just use it)
๐Ÿ“Œ EXAM TIP โ€” Step Order for Every EVM Question

Step 1: Find or calculate EV first. Step 2: Find or calculate PV. Step 3: Note the AC and BAC given. Step 4: Plug into whichever formula the question is asking for. Never skip Step 1.


9. Quick Summary โ€” Everything at a Glance

Term / FormulaWhat it meansExam trigger
BACTotal approved project budget“total budget” / “original budget”
PVBudgeted value of planned work“what we planned to have done”
EVBudgeted value of completed work“what we actually got done”
ACActual money spent“what we actually spent”
CV = EV โˆ’ ACCost variance โ€” positive = under budget“over / under budget by how much”
SV = EV โˆ’ PVSchedule variance โ€” positive = ahead“ahead / behind by how much”
CPI = EV รท ACCost efficiency โ€” >1 good, <1 bad“cost efficiency” / “for every rupee spent”
SPI = EV รท PVSchedule efficiency โ€” >1 good, <1 bad“schedule efficiency” / “how far ahead / behind”
EAC = BAC รท CPIExpected final project cost“how much will the project cost in total”
ETC = EAC โˆ’ ACCost still needed to finish“how much more money is needed”
VAC = BAC โˆ’ EACFinal surplus or overrun“will we finish over or under budget”
TCPI = (BACโˆ’EV) รท (BACโˆ’AC)Efficiency needed in remaining work“what CPI do we need going forward”
Contingency ReserveFor known risks โ€” PM controls“known risk” / “identified risk”
Management ReserveFor unknown surprises โ€” management controls“unknown risk” / “unexpected event”
Cost BaselineBudget excluding Management Reserve“approved budget for measurement”

๐ŸŽฏ Practice Q&A โ€” Test Yourself

Think of your answer first. Then click to reveal.

Q1. CPI = 0.85. What does this mean in plain English?
Answer: The project is over budget. For every โ‚น1 spent, only โ‚น0.85 worth of work is being delivered. The team is spending more than the value they are producing. CPI < 1 is always bad for cost.
Q2. SPI = 1.2. What does this mean?
Answer: The project is ahead of schedule. 20% more work has been completed than was planned at this point. SPI > 1 is always good for schedule.
Q3. BAC = โ‚น1,00,000. 6 months into a 10-month project. 50% of work is done. AC = โ‚น45,000. Calculate CPI and SPI.
Step 1 โ€” EV: 50% ร— โ‚น1,00,000 = โ‚น50,000
Step 2 โ€” PV: 6รท10 = 60% planned. PV = 60% ร— โ‚น1,00,000 = โ‚น60,000
CPI = EV รท AC = โ‚น50,000 รท โ‚น45,000 = 1.11 โ†’ Under budget โœ…
SPI = EV รท PV = โ‚น50,000 รท โ‚น60,000 = 0.83 โ†’ Behind schedule โŒ
Q4. What is the difference between Contingency Reserve and Management Reserve?
Contingency Reserve = extra money for known, identified risks. Controlled by the Project Manager. Included in the Cost Baseline.

Management Reserve = extra money for unknown surprises โ€” things nobody anticipated. Controlled by senior management. NOT included in the Cost Baseline โ€” added on top to get Total Project Funding.
Q5. EAC = โ‚น90,000. AC = โ‚น35,000. What is ETC?
Answer: ETC = EAC โˆ’ AC = โ‚น90,000 โˆ’ โ‚น35,000 = โ‚น55,000. This is the amount of money still needed to complete the remaining project work.
Q6. BAC = โ‚น1,00,000. EAC = โ‚น1,10,000. What is VAC and what does it mean?
VAC = BAC โˆ’ EAC = โ‚น1,00,000 โˆ’ โ‚น1,10,000 = โˆ’โ‚น10,000. Negative VAC means the project will finish over budget by โ‚น10,000. A negative VAC = cost overrun = bad news for the project.
Q7. The project has an unexpected government audit that was never anticipated in planning. Which reserve is used to fund this?
Answer: Management Reserve. This is an unknown, unanticipated event. Management Reserve covers exactly this โ€” surprises that nobody planned for. The PM must get management approval to access it. Contingency Reserve is only for known, identified risks.
Q8. What does TCPI > 1 tell the project manager?
Answer: TCPI > 1 means the team must work more efficiently in the remaining work than they have been so far โ€” just to finish within the original budget. The higher the TCPI, the harder it is to recover. TCPI = (BAC โˆ’ EV) รท (BAC โˆ’ AC).

โœ… Page 4 complete. Next up: Page 5 โ€” Risk Management โ€” Risk response strategies, Risk Register, probability & impact matrix, and Agile risk handling.

Scroll to Top