ClearPMPExam FormulasPractice Q&A Quick ReviseCalculators AI Tutor

Earned Value (EVM) Calculator

Enter BAC, PV, EV and AC to instantly get CV, SV, CPI, SPI, EAC, ETC, VAC and TCPI, with plain-English meaning for the PMP exam.

CV · SVCPI · SPIEAC · ETC · VACTCPI

Calculator

How earned value works

Earned Value Management compares three numbers: what you planned to do (PV), what you actually did (EV) and what it actually cost (AC). Everything else is a ratio or difference of these.

MeasureFormulaGood when
Cost VarianceCV = EV − ACpositive
Schedule VarianceSV = EV − PVpositive
CPIEV ÷ AC> 1
SPIEV ÷ PV> 1
EACBAC ÷ CPI (default)—
ETCEAC − AC—
VACBAC − EACpositive
TCPI(BAC − EV) ÷ (BAC − AC)≤ 1

Exam tip

Read the question for the trigger phrase: "current variance will continue" → BAC÷CPI; "variance was a one-off / atypical" → AC + BAC − EV; "both cost and schedule performance influence the outcome" → the CPI×SPI formula.

Frequently asked questions

What is a good CPI and SPI?

A CPI or SPI of 1.0 or higher is good. Below 1.0 means over budget (CPI) or behind schedule (SPI).

Which EAC formula should I use on the PMP exam?

Use BAC ÷ CPI when current cost performance is expected to continue. Use AC + (BAC − EV) when the variance was a one-time event. Use AC + (BAC − EV) ÷ (CPI × SPI) when both cost and schedule affect the result. If a new estimate is given, use AC + bottom-up ETC.

What does a TCPI greater than 1 mean?

It means the team must be more efficient than so far to finish within the target. The higher it is above 1, the harder the recovery.

More free PMP calculators

Learn the concept behind the numbers: PMP formulas explained · Practice Q&A · Quick Revise