Risk EMV Calculator

List your risks with probability and impact. See each risk's expected monetary value, total exposure and a suggested contingency reserve.

Probability × ImpactThreats & opportunitiesContingency reserve

Calculator

RiskProbability %Impact $ (threat −, opportunity +)EMV

Expected Monetary Value

EMV = Probability × Impact. Use negative impact for threats and positive for opportunities. Adding up all EMVs gives the net expected effect of your risks, a core input to decision tree analysis and to sizing the contingency reserve.

Exam tip

Contingency reserve is part of the cost baseline and is controlled by the project manager. Management reserve sits outside the baseline and needs management approval to use.

Frequently asked questions

Is EMV quantitative or qualitative analysis?

Quantitative. Qualitative analysis uses probability-impact matrices; EMV puts a number on risk using money.

What is the difference between contingency and management reserve?

Contingency reserve handles identified risks and is inside the cost baseline. Management reserve handles unknown-unknowns and is outside the baseline.

How do I use EMV in a decision tree?

Calculate EMV for each branch (probability × payoff, minus the cost of the option), then choose the option with the best net EMV.